Construction Public Notice
2403 San Pablo Ave., Berkeley CA
Project Description:
· Construction of a 4-story building, consisting of 36 apartment units.
Construction Activities:
Major phases of construction to include the following –
· Demo of existing building and hardscape.
· Excavation and grading to follow for preparation of the building foundation.
· Underground utilities.
· Forming and subsequent pouring of concrete foundation and podium
· Four stories of vertical framing including exterior and interior building finishes
· Site improvements including landscape, sidewalks, etc.
· Daily construction activities one can expect are use of hand tools (hammer, drills, etc.), hauling and hoisting of material, construction equipment such as backhoes, reach lifts, compressors, etc.
Anticipated General Schedule and Construction Phases:
· Concrete Construction (May 2025 – August 2025)
· Framing (September 2025 – January 2026)
· Façade and Finishes (January 2025 – June 2026)
· Site Improvements, Landscaping, Sidewalks, Etc. (July 2026 – December 2026)
Daily Construction Schedule:
· Work will Commence 7am-6pm Monday through Friday
· This project is approved for Saturday work if needed 9am – 4pm.
· Expected Start: May 2025
· Expected Finish: December 2026
Noise Management Individuals:
· Mark Edwards (510) 426-0004